Tuesday, November 24, 2009

November 2009. Recycled vinyl roof shingles installed.

Linda's and my good friend, Marshall Hatch, arrived from NH on Saturday afternoon, November 14. David King came out for the day on Sunday and the four of us spent the day getting the staging set. We needed to get a heavy platform up on the south side, scaffolds on the north, and Marshall's million and one tools (not to mention the nearly 70 bundles of shingles) up onto the west roof. We had some issues with power and rain, but Marshall is never one to slow down, so things were always proceeding. He worked many nights using only a headlamp to keep things moving.

The shingles are made of 80% post-consumer vinyl and are warranted to last 50 years.

Click on any image below to enlarge it a bit.

David braces the ladder for Marshall as he takes the platform up.


David and Marshall set the other end of the platform.


Marshall adjusts the platform. He'll use this to start the south side of the roof.


Marshall made a 'shingle sled' that David and I used to run shingles up a tilted ladder.


Shingles needed to be blended (to avoid bad color distribution on the roof) and also bent for optimal installation. Here we are on the staging area, the north roof is to the right, next to Marshall.


After completing the south roof in two days (Monday-Tuesday) there was a lot more preparation (and rain) for the north roof. Here Marshall built a vent pipe chimney to allow plumbing, solar hot water, and photo voltaic pipes to be installed in the future without having to drill into the roof later on. Brilliant.


Scaffolds on the north side with Marshall building the chimney, seen from below.


Billy assists Marshall as he drills a hole for our masonry stove pipe.



From the west, a shot of Billy assisting Marshall as he drills a hole for our masonry stove pipe.


Marshall, roped up and snapping a line. Ready to shingle.


Billy walks the plank, helping to snap a line across the roof.


Overcoming her discomfort with the height and exposure of the platform, Linda worked on the south side applying waterproof layers to the roof beams...


Scot then attached the lathe...


.. and Linda went back up to apply lime plaster.


There were a few late nights, roofing by flood lamp and head lamp.


Marshall custom fitting a water diverter.


Marshall planning out the next phase of the installation.

Billy assists by staging and passing shingles while Marshall nails.


Closer: Billy assists by staging and passing shingles while Marshall nails.


A shot of the south roof, complete except for the ridge tiles.


Marshall removing a final bracket from the south roof.

Some photos of the finished product will be posted soon. More to come.

Sunday, September 13, 2009

2009, August/Sept:
Stone, Lime Plaster, and Living Roofs.


West end with first coat of lime plaster, taken from the northwest at the end of September, 2009.


West end at the end of Sept 2009... and a little surrounding mess!


Marty planting on the barrel roof, the 2nd earth roof.


Marty and Linda planting on the barrel roof.


Mike Parsons working on the dining room stone wall.



Mike's work on the south, entry wall.



Mali, Denali and Ankur applying lime plaster to the west wall.

Linda plastering the west wall. Note the early 'tree' being placed in the plaster.


The bedroom wall mid Sept 2009: This shows a couple of phases at once.... One side straw, the other with a first coat of lime plaster.


North wall of the living room with first layer of lime plaster.
The window hole is 4' X 5'.


Living room, south wall before plastering. (note the waterproof and drainage layers have been applied to the barrel roof.)


The same wall with a partial first layer of lime plaster. The window - facing south - is 5' X 5'. Now the roof has soil and burlap on it.


Denali and Mali beginning to plant on the guest room roof.
Note the curved fascia boards above Denali's head, and the lime plaster wall behind.


Denali planting some chives. Lime wall behind is scored in anticipation of another coat.


Mali planting some thyme.


The guest room fully planted, with lime plaster wall behind coated twice. Now we wait and see how it grows.

Mid September we had a small work party to haul soil up to the barrel roof. Billy, Linda, Ankur, and Mali on the roof while....

Drew, Liv, Lindsay, and Denali fill and hoist soil up.

Monday, August 10, 2009

2009, June and July:
Straw Bale and Lime Plaster

In June, 2009 the straw bales arrived. Then in June and July we had a number of work weekends in which many people came to help.... as well as to learn some straw bale techniques.

In mid-June, the 660 straw bales arrived.


Sigi demonstrates how to bevel a straw bale.


The first row of the living room arch goes up.


The second row of the living room arch goes up.


The third row goes up and the arch is secure!


Here are the workers around the finished arch!


Meanwhile, in the bedroom, there is discussion about the curved wall.


Work on the curved wall begins.


The curved wall as seen from the outside.


Todra, Jay and Denali get ready to lay the 4th course.


Two days hard work and most of the curve is done.


A couple weeks later it is done.... awaiting windows.


Paul and Paola work on a side wall that adjoins the bedroom curve.


Folks work on the back (stairwell) wall.

The living room walls around the arch are nearly done.
They await a 4X5 foot window.


Friends come to help us plaster a wall with lime plaster.


Applying lime plaster to the barrel roof....

... wasn't all work.

Sunday, March 15, 2009

2009, Spring. Carpenters at work. Barrel roof goes up.

In mid March, a design 'irregularity' was discovered and some re-working of the second floor roof had to be done. John, Keith and Jimmy had to re-do a lot of work, but it is a beautiful sight to see. Here are images of the roof work, and final shots of the barrel roof.

March 2009. All the roofs are up! Plastic on the ground is some stone work that Linda and Scot have begun. What follows are some shots of all that work in progress.


Jimmy and Keith (up high) discuss issues with John (on the ground.) Note the curved board above John's head. That will be where the barrel roof begins over the living room.


John Edmonson setting a ladder scaffold.

Closer shot of Jimmy and Keith at work up high.


Keith and Jimmy build the knee wall that will support the barrel roof.

Keith and Jimmy on the knee wall.


2X12s rest on the knee walls of the barrel roof in an early shot.


Knee wall and barrel roof framing.

Soffet sections go on the barrel.

Inside, looking up at the barrel roof.

View from the south with all the roofs up.


Sunday, March 1, 2009

2009, March. The Radial Roof goes up.

In late February John Edmonson and his crew of skilled carpenters put up the radial roof over the master bedroom. We had originally planned on covering the joist structure, but upon seeing the beauty of the radial work, we now plan on exposing the beams. Here are a few shots of it.

Linda standing under the radial roof, showing the radial design that will show in the bedroom.


Radial roof seen from the second floor guest room area.


The design as seen from directly below (where the bed will be.)


Structure as seen from up on the roof.

Wednesday, February 25, 2009

2009, Feb. Second Floor Posts and Beams. Roofs go up.

With spring 2009 around the corner, the house is making progress. Posts and beams are up on the second floor, a couple of roofs are on and we hope to begin placing stone by mid-late March. Here are some shots showing recent progress. Most of the lumber is certified as sustainably harvested.


After the floor joists were put in, the second floor posts went up.


Guest room roof goes on, with 2nd floor posts showing. The roof will be a green roof... later.


Curves require that each joist is a different length.


The 12X14 inch oak beam over the master bedroom. It is a beauty! A radial roof will go above.


The roof begins on the western end. This will be a green roof.


Second floor beams go up!

Second floor roof goes up!


Monday, January 5, 2009

2008, December. First floor posts and beams.

What follows are a few photos of the posts and beams of the first floor.

Entry way. Looking through the living, dining and kitchen areas.


Looking at the house from the south.
Bath area and bedrooms are on the left,
while the living, dining, and kitchen areas are in the center.
To the extreme right is a small guest room.

Looking west from the back of the house.
On the left is the living, dining, kitchen area.
Straight ahead is the master bedroom.


The guest room.